NIPPON STEEL CORPORATION

Aging examples

Product name:Sound insulation device for Shinkansen steel beam bridge (3S sheet)

Project name,installation site

Iwabuchi overbridge, Tokaido Shinkansen

Date of construction

2006 / 12

Date of investigation

2023 / 02

Duration

16 Years

Specification of ZAM

2.3mm K27 ZC treatment

Photo of the project(early years)

main.jpg

3S sheet installation place (Iwabuchi overbridge)

Photo of the project (Aging)

  • 新幹線防音パネル1.JPG
  • aging1.jpg
  • aging2.jpg
  • aging3.jpg